Schedule:

Covered area:

June 2021: start of works

October 2021: completion of works

 

Gymnasium:

July 2021: start of works

November 2023: completion of works

 

Contracting authority:City of Paris

Total budget: €3 million, including SOLIDEO grant: €1.35 million